Start here: the Irish self-build and renovation journey
You don't need to understand construction to run a good project. You need to know what happens in what order, who signs off each step, and which steps can't be undone. This page covers all of it in 12 stages. Each stage has matching tasks in the checklist.
The four steps you can't undo
- Planning. Work that needs planning permission must not start until you have it (Citizens Information).
- Commencement Notice. It must reach the Building Control Authority 14 to 28 days before work starts. You can't submit it after you've started (council FAQ).
- SEAI grants. You must have grant approval before you start the upgrade works. Grants are never backdated (SEAI).
- Health and safety roles. If more than one contractor will work on your home, you must appoint a PSDP and a PSCS in writing (HSA).
1. Brief, budget and money
Write down what you want, then work out what it will really cost. Include VAT, fees and a contingency. Most construction services in Ireland are charged at the 13.5% reduced VAT rate (subject to the "two-thirds rule"). Professional fees (architect, engineer, surveyor) are charged at the 23% standard rate. Supply and installation of a heat pump system is at 9% (Revenue: current rates; Revenue: construction services; Revenue: heat pumps).
First-time buyer self-building a new home? Help to Buy can refund up to €35,000 for self-build mortgages first drawn down between 7 October 2026 and 31 December 2029. The approved valuation must be €500,000 or less and other conditions apply (Revenue; Revenue: who can claim).
The first budget for the house behind Teach assumed an 85 m² extension. When the tender drawings arrived, the extension measured 125.6 m², almost 50% bigger, and the estimate rose accordingly. Lesson: re-run your budget the day you get measured drawings.
2. Planning permission
Many extensions need planning permission. Since 27 July 2026, a rear extension can be exempt up to 45 m² in total (it used to be 40 m²). The 45 m² counts all previous extensions too, and there are limits on height, distance from boundaries and garden space (Citizens Information: altering your house). New houses always need permission.
The process: place a newspaper notice and a site notice (up for at least 5 weeks), and apply within 2 weeks of the newspaper notice. The fee is €34 for an extension or €65 for a house. The council generally decides within 8 weeks, longer if it asks for further information, and there's a 4-week appeal window (Citizens Information: planning permission). You can apply online through the national planning portal.
3. Design, engineer and safety roles
Planning drawings aren't construction drawings. Your engineer or architect produces the structural drawings, specifications and details that a builder can price and build from. Two sets of legal roles matter at this stage:
- Building control (BCAR): a new home, or an extension of more than 40 m², needs a Commencement Notice with compliance documentation. That means a design certificate, an Assigned Certifier who inspects and certifies the work, a builder's undertaking and an inspection plan. For a single dwelling or an extension over 40 m², an owner can choose to opt out of statutory certification, but must still comply with the Building Regulations (South Dublin County Council; SDCC: opt out; gov.ie: building control).
- Health and safety: if more than one contractor will work on the project, the homeowner must appoint a PSDP (Project Supervisor Design Process) before design starts and a PSCS (Project Supervisor Construction Stage) before construction starts (HSA: home owners).
Houses on a septic tank: an extension can mean a bigger wastewater treatment system and a new percolation area. Your designer will test the site (EPA: waste water).
4. SEAI grants and BER: plan them before you build
SEAI grants cover insulation, windows and doors, heat pumps, solar PV, batteries and more. You can apply individually and manage the work yourself, or go through a One Stop Shop that manages it for you and can offer a wider range of grants. Approval must be in place before works start (SEAI). Read the full guide: How to get every SEAI grant.
5. Tender and contractors
Send identical drawings, specification and pricing schedule to 3-5 builders or trades. Give them a return date, answer questions in writing to all of them, and compare the quotes line by line. Read the guide: How to tender a house renovation in Ireland. There are ready-made templates to help.
6. Building control: Commencement Notice
Everyone involved (owner, designer, builder, Assigned Certifier) registers on the Building Control Management System (BCMS), and the notice goes in 14-28 days before work starts (council FAQ). Starting without a required notice is an offence, and the notice can't be submitted afterwards (council FAQ).
7. Groundworks and structure (including steel)
This stage covers foundations, drainage, the floor slab, walls and any structural steel. Your engineer or Assigned Certifier inspects key stages before they're covered up. Modern open-plan extensions often need a lot of steel. See Structural steel for an extension.
8. Roofing and weathertight
Roof structure, covering, flashings, roof windows, gutters, then the windows and external doors. Once the building is "weathertight", the inside trades can start. Order long-lead items such as large glazing early.
9. First fix, insulation and second fix
First fix is the cables, pipes and ducts that go inside walls and floors. Then come insulation, the airtightness layer and plaster or drylining. Second fix is sockets, switches, sanitaryware, the kitchen, doors and skirting. Photograph everything before it's covered.
10. Budgets, cashflow and stage payments
Builders are usually paid in stages as work is done, often against a valuation certified by your architect, engineer or QS, with a small percentage held back as retention until defects are fixed. These terms come from your contract, not from law. Agree them in writing.
The tender for the Teach project used a standard RIAI form of building contract with 5% retention. The main contractor was asked to provide the PSCS. SEAI grants arrive as credits after the work, so in your cashflow plan you pay the full cost first and get the grant back later (unless you use a One Stop Shop, which deducts the grant up front, according to SEAI).
11. Procurement and long-lead items
Glazing, kitchens, stairs, heat pumps and steel can take weeks or months. Fix the specification and order them in time for the programme. Get supply-only items priced separately, because supply of most building materials is at the 23% standard VAT rate while supply-and-fit construction services are generally at 13.5% (Revenue: construction services).
12. Snagging, handover and certificates
Walk every room with a snag list before the final payment. Where the BCAR "additional requirements" apply, a Certificate of Compliance on Completion signed by the builder and Assigned Certifier must be lodged and on the public register before the building is occupied (council FAQ; gov.ie). For grant-aided work you need a post-works BER and signed SEAI paperwork before the grant is paid (SEAI: heat pump grant). Keep the safety file, certificates and warranties. You'll need them when you sell.