How to tender a house renovation in Ireland: a step-by-step for non-builders

"Tendering" just means asking several builders to price exactly the same job, on the same documents, by the same date, so you can compare like with like. Done well, it's the single biggest lever a homeowner has on cost and risk. Done badly, you end up with three quotes for three different houses.

This guide follows the tender for a real renovation and two-storey extension in Galway in late 2026, anonymised.

Step 1: Decide your route (main contractor or trade packages)

There are two common ways to buy a building project:

The Galway project first planned 12 direct-to-trade packages: strip-out, groundworks, structure/steel, envelope, roofing, glazing, electrical and PV, plumbing and heat pump, insulation and plaster, joinery, floors and decoration, externals. Glazing, the heat pump and electrical were "soft-quoted" early because of long lead times. The owner later went to a main-contractor tender, with the contractor providing the PSCS. Both routes are valid. Pick the one you can realistically manage.

Step 2: Don't tender until the documents are ready

Builders can only price what they can see. Before asking for firm prices you need:

  1. Planning permission (or a clear decision that the work is exempt: Citizens Information).
  2. Drawings marked "for tender": architectural plans, sections and elevations, plus the structural drawings (foundations, steel, roof).
  3. A specification or construction notes: insulation, windows (U-values), heating, finishes.
  4. Answers on who is the Assigned Certifier and how building control works for your job. A new home or an extension over 40 m² needs a Commencement Notice with compliance documentation, unless you opt out (SDCC).

Before that point you can still ask for "soft" or budget prices to test the market, as long as everyone knows they aren't binding.

Step 3: Get your own pre-tender estimate

Know roughly what the job should cost before the quotes arrive. Use a quantity surveyor (QS) if you can. At minimum, measure the floor areas from the drawings and use published cost guides (the SCSI publishes rebuilding-cost guidance).

On the Galway project, the independent pre-tender estimate was built the same way a QS would do it. The floor areas were measured from the tender drawings (147.8 m² existing house plus 125.6 m² new extension). The work was then priced in 13 elements, with the PC sums added, then the contractor's overheads and profit, then VAT at 13.5%, and a low/mid/high range given for each line. Professional fees and a contingency were kept outside the building-contract figure, so the all-in budget was always higher than any tender. (The project's own figures are not published here.)

Example only (not this project): 180 m² × an assumed €2,400/m² = €432,000 measured works. Add 12% OH&P (€51,840) to get €483,840 ex VAT. Add 13.5% VAT (€65,318) for about €549,160 incl. VAT. Then add fees and a 10% contingency separately.

Step 4: Build the tender pack

Send every tenderer the same pack. A good pack contains:

A simple elemental breakdown (as used on the Galway tender): 1 Preliminaries & PSCS · 2 Demolition/strip-out · 3 Substructure (foundations, slab) · 4 Frame & upper floors (incl. steel) · 5 Roofs · 6 External walls & cladding · 7 Windows/doors install · 8 Internal walls, doors & joinery · 9 Finishes · 10 Mechanical (heating, plumbing, ventilation) · 11 Electrical · 12 External works & drainage · 13 Attendance on PC items.

The Galway pack had 13 PC sums: windows/doors/screens, kitchen and utility, PV panels, wardrobes, stairs, sanitaryware, tiling, timber flooring, carpets, blinds, shelving, light fittings and patio paving. The pre-tender check found that the window and screen allowance looked well below what whole-house triple glazing plus large screens really costs. If an allowance is too low, every tender looks cheaper than the real job, and the difference comes back later as a variation. Check each PC sum against at least one real quote before you tender.

Step 5: Shortlist and invite

Invite 3 to 5 builders who have done similar work recently. Ask for addresses of jobs you can look at and references you can ring. Give a realistic period to price (2–4 weeks is common for a house) and a fixed deadline.

Step 6: Handle questions fairly

When one tenderer asks a question, answer it in writing to all of them, without saying who asked. If you change a drawing, re-issue it to everyone with a new revision letter and, if needed, extend the deadline.

Step 7: Compare tenders line by line

Put every quote into the same table (quote comparison template). For each element, compare it with your estimate and with the other quotes. Then:

Step 8: Check the builder before you sign

Step 9: Agree the contract

Before work starts, agree in writing: the contract sum, the documents it's based on, start and completion dates, the payment stages (usually monthly or by milestone against a certified valuation), retention (often a few percent, held until the defects period ends), how variations are priced and approved, and who submits which building control documents. Then submit the Commencement Notice 14–28 days before start (council FAQ).