Phase 1: 12 trade packages and quote scopes
What we asked: "We're self-building with no main contractor. Split the job into packages that trades can price cleanly."
What it produced: a 12-package plan and one written quote scope per package (strip-out, groundworks, structure/steel, envelope, roofing, glazing, electrical and solar, heating and plumbing, insulation and plaster, fit-out, floors and decoration, externals), plus a staircase tender scope. Each scope has the scope of work, exclusions (so packages don't overlap), "please price" instructions and a SOFT/BUDGET flag until the drawings were issued for tender.
| # | Package | Depends on engineer? | Soft-quote early? |
|---|---|---|---|
| 1 | Residual strip-out | No | Only if needed |
| 2 | Groundworks, foundations, drainage, wastewater | Yes | Capacity only |
| 3 | Structure, steel, roof carcass | Yes | Capacity only |
| 4 | Envelope: stone, timber, render | Specs | Yes |
| 5 | Roofing (+ PV interface) | Specs | Yes |
| 6 | Glazing, link, sliders, balustrades | Long lead | Yes, early |
| 7 | Electrical + solar PV | Yes | |
| 8 | Plumbing, heat pump, UFH | Yes | |
| 9 | Insulation, airtightness, plaster | After weathertight | Later |
| 10 | Joinery, stairs, kitchen, bathrooms | Fit-out | Later / PC sums |
| 11 | Floors and decoration | Late | Later |
| 12 | Externals and landscaping | Parallel late | Yes |
How we checked it: we compared the package boundaries against the engineer's scope to avoid doubling up, and made sure every item on the drawings belonged to exactly one package.
What changed later: we eventually tendered to main contractors instead (see Where it fell short), but the package split became the structure of the tender pricing schedule.
Try it yourself: templates · How to tender