Stripping it out ourselves

By September 2026 we had done about 80% of the strip-out ourselves, leaving only the residual work for contractors.

Things to check before you start:

  • Project manager tracked the strip-out (about 80% done by us) and wrote the residual scope so contractors only price what's left.
  • It added the checks to the plan before anything else was disturbed: an asbestos survey for a house of this age, the septic assessment, and a measured survey with utilities located.
  • It flagged the risk of losing SEAI grants by starting work early, before the grants researcher had mapped them.

What we learned: DIY strip-out saves contractor time, but its biggest value was learning the house. We found the real wall make-up, floor levels and services before the designers finalised anything.