Phase 4: steel bill of materials
What it produced: a member-by-member steel schedule taken off 6 structural sheets and a bar schedule:
- 41 members (UB, UC, PFC and SHS sections, grade S275), each with location, section, quantity, length, kg/m, total kg, finish and drawing reference.
- Colour-coded: green = read from drawing, orange = assumed (with the reason why).
- Totals: about 5.6 t of fabricated steel (including itemised plates and a 10% connection allowance) and about 1.3 t of reinforcement.
- Seven questions for the engineer: undimensioned lengths, a duplicated plan sheet, conflicting beam sizes, undefined lintel types, post heights and foundations, finish and fire protection, and mesh quantity.
- Indicative per-tonne pricing for checking quotes (totals [AWAITING JAMES APPROVAL]).
How we checked it: we spot-checked weights (kg/m × length × quantity) by hand and sent the queries to the engineer before asking fabricators to price.
Full method: Structural steel for an extension.