Built with Grok Bot A family with no building experience, building our dream house with Grok Bot AI agents as our project team. Meet the team & see the work → Unofficial, not endorsed or sponsored by xAI.

Phase 2: the schedule

What it produced: a phase-by-phase programme with gates (things that must be true before the next phase can start) and a contractor call-up order. The durations are indicative. The engineer's programme replaces them once drawings are firm.

Phase Indicative duration Trigger / gate
0. Drawings, planning, soft quotes (planning wait) Now
1. Planning wait + tender firm-up overlaps Drawings issued "for tender"
2. Enabling and groundworks ~4-8 weeks Gate A: planning decision + construction drawings · Gate B: Commencement Notice / certifier
3. Structure to weathertight ~8-14 weeks Foundations signed off
4. Envelope and first fix ~4-8 weeks (overlaps) Weathertight
5. Second fix and fit-out ~6-10 weeks First fix inspected
6. Externals and close-out ~3-6 weeks (overlaps) Snag + completion certificates

Call-up order: groundworker → structure/steel → roofer → glazing → envelope / insulation / first fix (overlapping) → second fix and heat pump commissioning → joinery, kitchen, bathrooms → flooring and decoration → externals → snag and certifier completion.

How we checked it: against the statutory steps (planning, Commencement Notice 14-28 days before start (council FAQ)) and against lead times we heard when soft-quoting.

Use the checklist to track the same stages.