Project dashboard
Last updated: 18 November 2026 · Draft
Programme
| Stage |
Status |
| Brief and design intent |
✅ Done |
| Strip-out (owner-led) |
✅ ~80% done (Sep 2026) |
| Energy strategy (heat pump + PV) |
✅ Decided |
| Basement |
✅ Excluded |
| Tender drawings |
✅ Issued (Oct 2026) |
| Independent estimate |
✅ Done |
| Steel BOM + engineer queries |
✅ Done (Nov 2026) |
| SEAI grant mapping |
✅ Done (Nov 2026) |
| Tenders |
⏳ Due 20 Nov 2026 |
| Contractor appointed |
⬜ |
| Commencement Notice |
⬜ |
| Start on site |
⬜ Target early 2027 |
Open decisions
| Decision |
Options |
Owner |
Due |
| Which tender to accept |
Builder A / B / C |
James |
After tender review |
| SEAI route |
Individual grants vs One Stop Shop |
James |
Before contract |
| Engineer's answers on steel queries |
7 queries open |
Engineer |
Before fabrication |
| Window/screen allowance |
Keep PC sum vs. get firm quote first |
James |
Before contract |
| Wastewater system |
Depends on site test results |
Engineer |
Before groundworks |
Money
| Item |
Figure |
| Budget |
[AWAITING JAMES APPROVAL] |
| Independent estimate |
[AWAITING JAMES APPROVAL] |
| Accepted tender |
[AWAITING JAMES APPROVAL] |
| Actual cost to date |
[AWAITING JAMES APPROVAL] |
| SEAI grants secured |
[TBC] |